Operator notes
How to run it
-
["\t\t\t\t
- 1. Enter days, lines a day, walk per line and the loaded wage — that is today's pick cost. ", '\t\t\t\t
- 2. Set the walk the re-slotting removes; 32% is the published range for an ABC layout. ', "\t\t\t\t
- 3. Enter the vendor's capital, maintenance and throughput gain as quoted. ", '\t\t\t\t
- 4. Add the WMS integration and the downtime cost, which the quote usually leaves out. ', "\t\t\t\t
- 5. Read the buyer payback against the vendor's, then decide whether the machine is the first move. "]
Model logic
Annual hours = days × lines × (fixed seconds + walk ÷ speed) ÷ (3600 × utilisation). Slotting is priced against today's layout, and the automation only against the already-slotted one, so the walk seconds are not counted twice.